Task Constraint overview
Task constraints determine when a task should start and end on a project.
Overview of Task Constraints
As you build your project plan, you make decisions on the sequence and time frame of your tasks on the project. Tasks can function independently of any task sequence but they might impact the project timeline. Task Constraints allow a project manager to plan when certain tasks can start or complete on a project.
Depending on the constraint you use, you might have to specify a Planned Start Date, a Planned Completion Date, or both for the task.
Constraint types that require defined dates impact predecessor relationships.
The following table displays each constraint and its abbreviation. Abbreviations are used on task lists and when creating Kick-Start import files. Click the linked title of each task constraint for more information about that type of constraint.
Places the start time of the task as close to the beginning of the project as possible.
It is the default constraint if the project uses a Schedule Mode from Start Date and if the system default start date for a new task is set to Based on the Project Planned Date.
Places the completion time of the task as close to the end of the project as possible.
This is the default constraint when the project Schedule Mode is from Completion Date and the system or group default for the Start Date of a task is set to Based on the Project Planned Date.
Schedules a task to start after the date you specify.
This is the default constraint if the project Schedule Mode is from Start Date and if the system or group default Start Date for a new task is set to Today.
Schedules a task to start prior to the date you specify.
This is the default constraint if the project Schedule Mode is from Completion Date and if the system or group default for the Start Date of a task is set to Today.
Overview of default constraints
When you create new tasks, a Task Constraint is automatically selected by Workfront.
Workfront uses two variables to decide which Task Constraint is selected by default for a new task:
-
The Project Schedule From field on the project.
For information about the Project Schedule From field, see Edit projects.
-
The Start Date preference configured by your Workfront or group administrator in the Tasks & Issues area of Setup.
For information about Tasks & Issues Preferences, see the New Task Defaults section in Configure system-wide task and issue preferences.
The following table shows the default Task Constraint when choosing different variables for your project and your new tasks: