Calculate costs in the Resource Planner

You can budget your resources in the Adobe Workfront Resource Planner by using Cost values, instead of Hours or FTE values. Cost values are not available for the View by User view in the Resource Planner.

IMPORTANT
You must associate users and job roles with Cost per Hour rates in order to display Cost information in the Resource Planner.
For more information about associating Cost per Hour rates with job roles, see Create and manage job roles.
For more information about associating Cost per Hour rates with users, see Edit a user’s profile.

Before budgeting your resources, ensure you have a good understanding of what work needs to be done (Planned Hours, FTE, or Cost) and what time your users are open to work (Available Hours, FTE, or Cost).
For more information about understanding the information in the Resource Planner when budgeting by Hours or FTE, see Overview of hours, FTE, and cost information in the Project and Role views of the Resource Planner.

Access requirements

You must have the following:

Adobe Workfront plan*
Pro and higher
Adobe Workfront license*
Plan
Access level configurations*

Edit access to Resource Management that includes access to Edit priorities and budget hours in the Resource Planner

Edit access to Financial Data, Projects, and Users

NOTE

If you still don’t have access, ask your Workfront administrator if they set additional restrictions in your access level. For information on how a Workfront administrator can change your access level, see Create or modify custom access levels.

Object permissions

Manage permissions to the projects you want to budget information for with ability to Manage Finances

For information on requesting additional access, see Request access to objects.

*To find out what plan, license type, or access you have, contact your Workfront administrator.

Display information in the Resource Planner by Cost

By default, the availability and allocation information is displayed in Hours in the Resource Planner.

To display Available, Planned, and Budgeted information by Cost in the Resource Planner:

  1. Click the Main Menu icon in the upper-right corner of Adobe Workfront.

  2. Click Resourcing.

  3. Go to the Resource Planner.

  4. (Conditional) Select View by Project or View by Role.
    By default View by Project is selected.
    The allocation and availability information displays in Hours.

  5. From the Hours drop-down menu, select Cost.

    If you do not have access to Financial Data in your access level, this option is not available.
    If projects have a different currency than the system currency the Cost for these projects displays in the Resource Planner converted in the currency of the system. Your system administrator defines the system currency.
    For more information about setting up the system currency in Workfront and conversion rates, see Set up exchange rates.
    costs_in_the_planner_with_no_budgeting.png

Calculate Available Cost in the Resource Planner

To display Available Cost values in the Resource Planner you must have the following:

  • Cost per Hour rates for the users and roles

  • Information about user availability.

    Obtaining information about user availability depends on how your Workfront administrator configures the Resource Management Preferences.
    For more information about calculating user availability and setting Resource Management Preferences, see Configure Resource Management preferences.

The following table illustrates how Available Cost is calculated in the Resource Planner:

Available Cost
Calculation
User Available Cost

The Available Cost per user is calculated using the following formula:

Available User Cost = User Available Hours * User Cost per Hour Rate

NOTE

If the user does not have a Cost per Hour rate in their profile, the Cost per Hour rate of the job role under which they are listed is used in the calculation. If the user has no role associated with them, the Available User Cost is $0.

Role Available Cost

The Available Cost per role is calculated using the following formula:

Available Role Cost = Role Available Hours * Role Cost per Hour Rate

NOTE

If the role does not have a Cost per Hour rate, the Available Role Cost is $0.

Project Available Cost

The Available Cost per project is calculated using the following formula:

Available Project Cost = SUM(User Available Hours * User Cost per Hour Rate)

Calculate Planned Cost in the Resource Planner

Although you cannot view task information in the Resource Planner, the Planned Costs for users, roles, and the projects are calculated by taking into account the following task information:

  • The type of assignment on the task.
    You can leave a task unassigned, or assign the following entities to a task:

    • A User (with or without a Job Role)
    • A Role
    • A Team
      A task assigned to a Team is considered unassigned, from the perspective of the Resource Planner.
  • The Cost Type of the tasks on the project.
    For more information about the Cost Type of a task, see Track costs.

  • The effective dates of the cost rates for job roles and users.

    For example, if the role or user has 10 planned hours in February and 10 planned hours in March, but the cost rate has changed from $12 to $20 in March, the value for the Planned Cost in February is $120, and in March the Planned Cost is $200.

NOTE
User Planned Costs do not influence the Project Planned Cost. Only the Role Planned costs affect the Project Planned Costs, in the Resource Planner.

The following scenarios exist when calculating the Planned Cost for users, roles, and the project:

  • When the Cost Type is **User Hourly **and there is no assignment on the task:

    • Role and user Planned Cost:

      The Role and User Planned Costs are $0.00.

    • Project Planned Cost:

      The Project Planned Cost is $0.00.

  • When the Cost Type is User Hourly and there is a user assignment on the task:

    • Role and user Planned Cost:

      The User Planned Cost is calculated using the following formula:

      User Planned Cost Rate = User Planned Hours * User Cost per Hour Rate

      If a user has a cost rate in their profile, then that rate is used to calculate Planned Cost. Otherwise, the system-level Cost per Hour rate of their Primary Role is used.

      note note
      NOTE
      The user can be assigned to the task with one of their secondary job roles, but the rate of the primary job role is used here instead.

      The Role Planned Cost is calculated using the following formula:

      Role Planned Cost = SUM(User Planned Cost)

    • Project Planned Cost:

      The Project Planned Cost is $0.00.

  • When the Cost Type is User Hourly and there is a job role assignment on the task:

    • Role and user Planned Cost:

      The User Planned Cost is $0.00.

      The Role Planned Cost is calculated using the following formula:

      Role Planned Cost = Role Planned Hours * Role Cost per Hours

      The system-level Cost per Hour rate of the job role assigned to the task is used to calculate Planned Cost.

    • Project Planned Cost:

      The Project Planned Cost is $0.00.

  • When the Cost Type is Role Hourly and there is no assignment on the task:

    • Role and user Planned Cost:

      The Role and User Planned Costs are $0.00.

    • Project Planned Cost:

      The Project Planned Cost is $0.00.

  • When the Cost Type is Role Hourly and there is a user assignment on the task:

    • Role and user Planned Cost:

      The User Planned Cost is $0.00.

      The Role Planned Cost is calculated by the following formula:

      Role Planned Cost = Role Planned Hours * Role Cost per Hours

      Workfront looks at the job role that the user fulfills on the task to calculate the Planned Cost for the role.

      If the user is not associated with any role on the task, the Planned Cost is $0.00.

    • Project Planned Cost:

      The Project Planned Cost is calculated using the following formula:

      Project Planned Cost = SUM(Role Planned Costs)

  • When the Cost Type is Role Hourly and there is a job role assignment on the task:

    • Role and user Planned Cost:

      The User Planned Cost is $0.00.

      The Role Planned Cost is calculated by the following formula:

      Role Planned Cost = Role Planned Hours * Role Cost per Hours

      Workfront looks at the job role that the user fulfills on the task to calculate the Planned Cost for the role.

    • Project Planned Cost:

      The Project Planned Cost is calculated using the following formula:

      Project Planned Cost = SUM(Role Planned Costs)

Calculate Budgeted Cost in the Resource Planner

To display Budgeted Cost values in the Resource Planner you must have the following:

  • Budgeted Hours for roles, users, and projects.
  • Cost per Hour rates for users and roles.
NOTE
The Budgeted Hours for the projects are calculated based on the Budgeted Hours for the Roles, not those of users.

The following table illustrates how Budgeted Cost is calculated in the Resource Planner:

Budgeted Cost
Calculation
User Budgeted Cost

The Budgeted Cost per user is calculated using the following formula:

Budgeted User Cost = User Budgeted Hours * User Cost per Hour Rate

NOTE

If the user does not have a Cost per Hour rate in their profile, the Budgeted User Cost is $0.00.

Role Budgeted Cost

The Role Budgeted Cost is calculated using the following formula:

Role Budgeted Cost = Role Budgeted Hours * Role Cost per Hour Rate

NOTE

If the role does not have a Cost per Hour rate, the Budgeted Role Cost is $0.00.

Project Budgeted Cost

The Budgeted Cost per project is calculated using the following formula:

Project Budgeted Cost = SUM(Role Budgeted Cost).

recommendation-more-help
5f00cc6b-2202-40d6-bcd0-3ee0c2316b43